Scheduled Network Hardware Maintenance
Scheduled Maintenance Report for freistilbox
Completed
The scheduled maintenance has been completed.
Posted Dec 11, 2018 - 05:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 11, 2018 - 03:00 UTC
Scheduled
Our datacenter provider has announced that they will perform maintenance work on network hardware connecting our infrastructure on Tuesday, 2018-12-11 between 3 and 5 am UTC (4-6am CET).

In this maintenance window several of our servers in multiple data centers will be unreachable for up to 20 minutes. Therefore a reduced availability of the following systems can't be completely avoided:

* repo.freistilbox.net
* all shell boxes
* web sites of clusters: c105, c179 and c183
* web sites using our new edge router

All other components of the infrastructure are not affected. Edge routers, caching proxies, other application servers and databases will have no downtime.
Posted Dec 10, 2018 - 11:11 UTC
This scheduled maintenance affected: Network.