Scheduled Maintenance Report for freistilbox
Completed
The scheduled maintenance has been completed.
Posted Oct 19, 2017 - 04:02 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 19, 2017 - 03:00 UTC
Scheduled
Datacenter support informed us that they need to do urgent upgrades to several network routers Thursday, 2017-10-19 between 3 and 5am UTC (5-7am CEST).

One router upgrade affects one server providing memcached and will have an impact on connectivity of a maximum of 20 minutes. The clusters affected are: c53, c55, c56, c63, c64, c86, c104, c116, c141.

All other components of the infrastructure are not affected. Edge routers, caching proxies, application servers and databases will have no downtime.
Posted Oct 17, 2017 - 10:05 UTC